Plan, design and construct a sports plex and indoor recreation aquatic facility
Project Details
Expectations:
Complete design and begin construction of the indoor recreation and aquatic facility in Noble Park
Timeline:
2020 – 2021
Key Team Members:
James Arndt, City Manager’s Office
2019
ANNUAL REPORT
- Completed the RFQ process and selected a firm for the design of the Indoor Aquatic and Recreation Facility and for the design of the outdoor recreation facilities (baseball, soccer, and softball).
- Began design process for the facility
- Worked with the Board of Commissioners to raise the City’s Insurance Premium Tax from 6% to 7% effective July 1, 2020 and authorize the issuance of General Obligation Bond in the amount of $22 million for the
indoor recreation and aquatic center to include the costs of constructing and equipping the facility.
Quarterly Updates
Quarter
Completed Tasks
2020 Q3
- The Paducah Board of Commissioners approved a municipal order to continue the suspension of the agreement with Lose & Associates, Inc. regarding the design and construction management services for the Indoor Recreation and Aquatic Center until January 2021 and directed the City Manager to continue due diligence on the project.
2020 Q4
- The Paducah Board of Commissioners approved a municipal order to continue the suspension of the agreement with Lose & Associates, Inc. regarding the design and construction management services for the Indoor Recreation and Aquatic Center until January 2021 and directed the City Manager to continue due diligence on the project.