WIN INITIATIVE UPDATES

I-1
Continue to expand the Greenway Trail Corridor throughout the City
Project Details
Expectations:
Completion of the Bob Leeper Bridge and construction of Phase 5. Plan Phase 6 and apply for grant funding.
Timeline:
2020
Key Team Members:
Tammara Tracy & Rick Murphy
2019
ANNUAL REPORT
- Parks Master Plan established common bicycle standards and new greenway/multi-purpose paths.
- State adopted Small Urban Study
- Awarded BUILD Grant development includes Bike/Pedestrian/Broadband Linkages from the Convention Center to Riverfront.
- Completed Greenway Trail Phase 4.
Quarterly Updates
Quarter
Completed Tasks
2020 Q3
- Bob Leeper Bridge completed in August with ribbon cutting in September.
- Greenway Trail Ph 5 complete in August with ribbon cutting in September. Remaining landscaping & other features are part of the BUILD grant.
- City Manager establishing grant development team for Phase 6.
2020 Q4
- Bob Leeper Bridge completed in August with ribbon cutting in September.
- Greenway Trail Ph 5 complete in August with ribbon cutting in September. Remaining landscaping & other features are part of the BUILD grant.
- Grant development team met to identify possible phase and funding opportunities and exploring options to connect the southside floodwall to the downtown.