WIN INITIATIVE UPDATES

Our Growth

I-1

Continue to expand the Greenway Trail Corridor throughout the City
Project Details

Expectations:
Completion of the Bob Leeper Bridge and construction of Phase 5. Plan Phase 6 and apply for grant funding.

Timeline:
2020

Key Team Members:
Tammara Tracy & Rick Murphy

2019
ANNUAL REPORT

  • Parks Master Plan established common bicycle standards and new greenway/multi-purpose paths.
  • State adopted Small Urban Study
  • Awarded BUILD Grant development includes Bike/Pedestrian/Broadband Linkages from the Convention Center to Riverfront.
  • Completed Greenway Trail Phase 4.
Quarterly Updates

Quarter

Completed Tasks

2020 Q3

  • Bob Leeper Bridge completed in August with ribbon cutting in September.
  • Greenway Trail Ph 5 complete in August with ribbon cutting in September. Remaining landscaping & other features are part of the BUILD grant.
  • City Manager establishing grant development team for Phase 6.

2020 Q4

  • Bob Leeper Bridge completed in August with ribbon cutting in September.
  • Greenway Trail Ph 5 complete in August with ribbon cutting in September. Remaining landscaping & other features are part of the BUILD grant.
  • Grant development team met to identify possible phase and funding opportunities and exploring options to connect the southside floodwall to the downtown.
Our Growth
OUR GROWTH

Building Paducah in both our private lives and our public institutions.

Our Community
OUR COMMUNITY

Making our neighborhoods safer, cleaner and more connected.

Our Engagement
OUR ENGAGEMENT

Connecting residents with each other and their representatives.

Our Culture
OUR CULTURE

Bringing the world to Paducah and Paducah to the world.