Continue implementation of the USACE/City of Paducah $32m Local Flood Protection Project (LFPP) Restoration
Project Details

Expectations:
Replacement of discharge pipes & the slice gate, rehabilitation of various mechanical components and motors at Pump Station #2

Timeline:
2020 – 2022

Key Team Members:
Rick Murphy

Quarterly Updates

Quarter

Completed Tasks

2020 Q3

  • Contract for Pump Station #2 terminated, rebid and awarded. New project schedule approved. Work has restarted- expected completion date December 2021.
  • LFPP Phase 1 work on-going with expected completion date of 2/15/2022.
  • LFPP Phase 2 work on-going with expected completion date of 2/15/2022.
  • Floodwall Seal Closure project in design.

2020 Q4

  • Contract for Pump Station #2 terminated, rebid and awarded. New project schedule approved. Work expected completion date December 2021.
  • LFPP Phase 1 work on-going with expected completion date of 3/15/2022.
  • LFPP Phase 2 work on-going with expected completion date of 2/15/2022.
  • Floodwall Seal Closure project design complete; construction bid expected in Jan 2021
  • Flap Gate Replacement project RFQ complete- professional services contract expected in Jan 2021
Our Growth
OUR GROWTH

Building Paducah in both our private lives and our public institutions.

Our Community
OUR COMMUNITY

Making our neighborhoods safer, cleaner and more connected.

Our Engagement
OUR ENGAGEMENT

Connecting residents with each other and their representatives.

Our Culture
OUR CULTURE

Bringing the world to Paducah and Paducah to the world.